Luo Jiman,Liu Zeming,Yin Hui,et al.Scheme Design and Kinematics Analysis of Single Leg Mechanism of Multi-legged Robot[J].Journal of Mechanical Transmission,2021,45(11):71-78.
Luo Jiman,Liu Zeming,Yin Hui,et al.Scheme Design and Kinematics Analysis of Single Leg Mechanism of Multi-legged Robot[J].Journal of Mechanical Transmission,2021,45(11):71-78. DOI: 10.16578/j.issn.1004.2539.2021.11.012.
Scheme Design and Kinematics Analysis of Single Leg Mechanism of Multi-legged Robot
In order to realize the monitoring and maintenance of the internal environment of the pipeline,a cam-linkage mechanism is designed as a multi-legged pipeline robot,and the motion analysis and mechanism improvement of the single-leg mechanism are carried out,so as to improve the shortcomings of the initial connecting rod mechanism,such as low motion precision and large inertia force. The mechanism scheme is theoretically modeled,and then the motion analysis of the mechanism is carried out by using the method of the joint simulation of 3D modeling software SolidWorks and motion analysis software Adams. The mechanism is improved by changing relevant parameters of the mechanism. Through comparative analysis,it can be seen that the cam-linkage scheme has more advantages than the initial scheme. Change the size of the cam,the foot of the mechanism in the normal direction of the displacement of the greater,the foot will be lifted higher,and the same time can walk a longer distance. The results also show that the cam-linkage mechanism has less inertia force and impact,more stable operation,and easy to realize specific motion law.
关键词
管道机器人凸轮SolidWorksAdams
Keywords
Pipeline robotCamSolidWorksAdams
references
刘甫,杨浩奕.管道机器人自适应变径设计[J].南方农机,2020,51(17):125-126.
LIU Fu,YANG Haoyi.Adaptive diameter reduction design of pipeline robot[J].China Southern Agricultural Machinery,2020,51(17):125-126.
WANG Jingdong,WANG Jiaqi,CHEN Guangjun,et al.Design and simulation of cam mechanism in cleaning-robot for pipe inner surface[J].Journal of Changchun University of Science and Technology(Natural Science Edition),2019,42(5):52-56.
KAKOGAWA A,MA S.Design of a multilink-articulated wheeled pipeline inspection robot using only passive elastic joints[J].Advanced Robotics,2018,32(1):37-50.
SINGH T,TIWARI D R,ANAND P,et al.Pipe inspection robot[J].Invertis Journal of Science & Technology,2019,12(2):34-36.
MIRO J V,ULAPANE N,SHI L,et al.Robotic pipeline wall thickness evaluation for dense nondestructive testing inspection[J].Journal of Field Robotics,2018,35(8):1293-1310.
YAMAMOTO T,KONYO M,TADAKUMA K,et al.High-speed sliding-inchworm motion mechanism with expansion-type pneumatic hollow-shaft actuators for in-pipe inspections[J].Mechatronics,2018,56:101-114.
SAVIN S,JATSUN S,VOROCHAEVA L.State observer design for a walking in-pipe robot[J].MATEC Web of Conferences,2018,161:261-266.
RASHID M Z,YAKUB M F M,SALIM S A Z S,et al.Modeling of the in-pipe inspection robot:A comprehensive review[J].Ocean Engineering,2020,203:40-45.
HEMAVATHI R,PUSHPALATHA B A.Crack and object detection in pipeline using inspection robot[J].Journal of Trend in Scientific Research and Development,2018,2(6):66-70.
LUO Jiman,ZHANG Dongyue.Design and kinematics simulation of a new step-type pipeline robot[J].Development & Innovation of Machinery & Electrical Products,2016,29(5):8-11.
Research and Simulation of Cornering Characteristics on Oil and Gas Pipeline Robots
Stability Analysis and Simulation of Multi-section Pipeline Robots in the Turning Process
Structure Design and Simulation Analysis of the Dynamic Inspection Instrument for Middle and Large Worm Gear Pairs
Structural Design and Analysis of Adaptive Pipe Diameter Full Drive Pipeline Robots
Kinematic and Dynamic Analysis of an Eight-bar Mechanism in Carton Forming
Related Author
No data
Related Institution
Wuhan Qinling Lingke Aviation Power System Co., Ltd.
School of Mechanical and Electrical Engineering, Hubei Green Chemical Equipment Engineering Technology;Research Center of Wuhan Institute of Technology
College of Mechanical Engineering and Automation, Liaoning University of Technology
Chongqing Key Laboratory of Time-Grating Sensing and Advanced Testing Technology,Chongqing University of Technology
Engineering Research Center of Mechanical Testing Technology and Equipment, Ministry of Education,Chongqing University of Technology